The Norwegian Government wants greater control over the development of data centers in Norway. At the same time, Statnett is putting parts of the process for new grid connections on hold. Developers and suppliers need to establish which parts of their projects can proceed as agreed, and where delays or changes to requirements may arise.

Statnett, which is responsible for developing, operating and maintaining Norway’s electricity transmission grid, has warned of future power shortages and pressure on the power system. The rapid growth in data centers in Norway is putting a strain on power supply, prompting Statnett to temporarily suspend new reservations of grid capacity. The suspension is expected to end no later than August 1, 2027. In parallel, the Government is working on a licensing scheme for data centers.

A new licensing scheme for data centers

The proposed licensing scheme is intended to give the authorities control over which data centers are established and the activities they carry out. The Government wants to prioritize capacity that serves Norway’s societal needs, including healthcare, emergency preparedness and communications. It has explicitly stated that data centers used for cryptocurrency mining are not wanted.

How the authorities will draw these distinctions remains unclear. Many data centers serve multiple customers with different needs, and their customer base may change without any alterations to the facility itself. The design of the licensing scheme will therefore matter both when a data center is established and throughout its operation.

The scheme is also intended to cover existing data centers, but with robust transitional arrangements. A proposal is expected in fall 2027, following a public consultation. No decision has yet been made on when any licensing requirement would take effect, or how projects already under construction would be treated.

Possible new requirements for developers

The Government is also considering requiring data center developers to contribute more toward grid investment and introducing requirements for developers to generate their own electricity. This could affect the financial viability of future projects, but no specific requirements have yet been set for businesses to plan around.

What Statnett has put on hold

Statnett’s measures have a more immediate impact. New reservations of grid capacity have been temporarily suspended, as has the processing of new applications for technical functionality approval under section 14 of the Norwegian Regulations on System Responsibility in the Power System (systemansvarsforskriften). For direct connections to the 420 kV grid, the processing of applications already submitted has also been paused. Statnett will clarify the requirements needed to ensure stable operation of the power system and expects to resume processing applications no later than August 1, 2027.

What the pause does not affect

These measures do not amount to a general halt to construction. Existing connections are unaffected, and facilities with the necessary technical approvals can still be connected. Applications for certain smaller facilities and some projects connecting to the regional grid that are due to start operating in the near future may still be processed. Projects are also to retain their position in the connection queue relative to other customers.

What developers and suppliers should do now

For each business, the first step should be to obtain written confirmation of the capacity reserved, the approvals granted and the matters still outstanding. This is particularly important for phased developments: the status of the first phase does not necessarily determine the position for later expansions.

The next step is to assess the project schedule against the contracts. Delays in securing a power supply can push back testing and handover, even if construction is otherwise on schedule. For suppliers, this may mean changes to delivery dates, having to keep personnel committed for longer and delayed payment. Each contract needs to be reviewed to establish who bears responsibility for these consequences and what notices must be given.

It is therefore too early to draw a single conclusion for the industry as a whole. Some projects can proceed, while others must await further clarification. The priority now is to establish a clear picture of your own project before committing to new orders, investments and deadlines.

Our lawyers have extensive expertise in the data center sector and can assist with reviewing contracts, obligations and related matters.[

Sigbjørn Sørensen - Lawyer & partner avatar
Sigbjørn Sørensen - Lawyer & partner
With more than 15 years of experience as a tax and business lawyer, Sigbjørn advises Norwegian and international companies, as well as individuals, on national and international tax matters and corporate law. He has extensive experience assisting international companies establishing or doing business in Norway, providing practical and strategic advice tailored to the Norwegian regulatory and tax landscape. His expertise includes corporate and personal taxation, reorganizations, mergers and demergers, business transfers, and transactions. Sigbjørn supports clients throughout all stages of the business lifecycle — from corporate structuring and governance matters to tax due diligence in connection with transactions, and tax audits, appeals, and disputes with the tax authorities.
Thea Slethaug - Lawyer avatar
Thea Slethaug - Lawyer
Thea is an experienced business lawyer with expertise in real estate law and corporate law, as well as tax matters for Norwegian and international companies and individuals. She has particular strength in contract law and corporate transactions, and extensive experience guiding real estate companies through every stage of their projects — from initial design through final sale.
Terese Eriksen Eldholm - Lawyer avatar
Terese Eriksen Eldholm - Lawyer
Terese is a seasoned labor law lawyer who specializes in labor law, assisting both Norwegian and international companies with employment matters to ensure compliance with Norwegian regulations. She also advises clients on corporate law, contract law, and GDPR, providing clear and practical legal guidance tailored to their business needs.

RELATED ARTICLES